# Agent Log: codex-task98-source-tests-20260222T021156Z-a1b2
- alias: `codex-task98-source-tests`
- mission: `Execute TASK-98 end-to-end via writing-plans + executing-plans flow (no commit).`
- status: `done`
- started_utc: `2026-02-22T02:11:56Z`
- backlog_task: `TASK-98`
## Intent
- Validate current TASK-98 state from Backlog MCP.
- Load writing-plans skill; produce end-to-end execution plan for remaining scope.
- Load executing-plans skill; execute plan, including code/test/doc/workflow updates if needed.
- Re-verify gates tied to TASK-98 and update backlog task AC/DoD notes/status.
## Planned Files
- `package.json`
- `.github/workflows/ci.yml`
- `.github/workflows/release.yml`
- `docs/development.md`
- `docs/subagents/INDEX.md` (own row only)
- `docs/subagents/collaboration.md` (append-only)
## Assumptions
- Existing in-progress rows/files from other agents remain authoritative for their own scope.
- TASK-98 may already include partial implementation; this run closes remaining verification/finalization.
## Activity Log
- `2026-02-22T02:11:56Z` started; backlog overview + TASK-98 loaded; subagent coordination files read.
- `2026-02-22T02:30:00Z` loaded writing-plans + executing-plans; saved closure plan at `docs/plans/2026-02-22-task-98-closure-source-dist-smoke.md`.
- `2026-02-22T02:35:00Z` validation gates PASS: `bun run test:fast`, `bun run build`, `bun run test:smoke:dist`.
- `2026-02-22T02:35:30Z` parallel subagent verification PASS: script split + CI/release/docs policy unchanged.
- `2026-02-22T02:36:00Z` backlog finalized: TASK-98 DoD #2 checked, notes appended with timing evidence, status moved to Done.
## Files Touched
- `docs/plans/2026-02-22-task-98-closure-source-dist-smoke.md` (new)
- `docs/subagents/agents/codex-task98-source-tests-20260222T021156Z-a1b2.md` (this file)
- `docs/subagents/INDEX.md` (own row)
- `docs/subagents/collaboration.md` (append-only)
## Handoff
- TASK-98 is now Done in Backlog.
- No code changes required in task scope during closure pass; implementation from prior run already aligned.